Bond Construction Update #2
Construction continues to move forward across several of our voter-approved bond projects, and we're excited to share another update.
As we get closer to the start of the school year, more of the work is becoming visible. While crews continue installing and testing the new HVAC system inside the middle/high school, we're also beginning to see progress on other bond projects, including elementary security upgradesand preparation for the new middle school cafeteria and WAY addition.
Progress This Week
Several important milestones were reached over the past week:
Installation of the new classroom heating and cooling units continues throughout the middle/high school.
Rooftop air-conditioning condensers have been installed, connected, and pressure
tested. Crews are now completing the electrical connections and control systems that
will allow the units to operate.
New electrical service has been installed to provide the additional power needed for
classroom air conditioning.
At the elementary school, the new secure entry improvements are nearly complete. Card
readers and magnetic locking hardware will be programmed, with final paint and finish
work wrapping up soon.
Site preparation has begun for the new middle school cafeteria addition, including
fencing, surveying, and utility marking. These early steps prepare the area for
construction to begin.
What's Happening Next
Over the coming weeks, construction crews will focus on:
Beginning startup and testing of the new HVAC equipment to ensure every classroom
system is operating properly before students return.
Completing the remaining electrical controls and wiring for the new heating and cooling
system.
Launching construction on the new cafeteria and WAY building addition behind the
middle school gym.
Looking Ahead
The next several weeks will be exciting as multiple bond projects continue moving forward.
Upcoming milestones include:
August 2026: Construction begins on the new middle school cafeteria and WAY building
addition.
Before the start of school: HVAC system startups, testing, and final inspections continue
to ensure classrooms are ready for students.
Spring 2027: Renovations to the high school girls' locker room are scheduled to begin.
Thank you for your continued patience and support as these projects move forward. Every improvement represents an investment in safer, more comfortable, and more modern learning environments for our students and staff. We look forward to sharing more progress with you in the weeks ahead.